To work out how many truckloads your dig will be, multiply the length, width and average depth in metres to get cubic metres in the ground, allow for the soil swelling once it is dug, then divide by what each truck can legally carry. The answer is almost always more trucks than the hole suggests.

That gap between the hole and the pile catches a lot of people out, and it is one reason two quotes for the same job can look so different. Here is the general method, so you can run the numbers on your own block before anyone gives you a price.

Start With the Volume in the Ground

The first number is the easy one. Measure the area you are digging and how deep it goes, in metres, and multiply them together.

A worked example. Say you are digging out a pad 10 metres long and 6 metres wide, 0.5 metres deep. That is 10 × 6 × 0.5, which comes to 30 cubic metres of soil in the ground.

Contractors sometimes call this the bank volume, or the in situ volume. It is the volume the soil takes up while it is still packed in place, before anyone has touched it. Everything else gets worked out from here, so it is worth getting right.

Working Out an Average Depth on a Sloping Block

Most blocks are not flat, which means the depth is not the same everywhere. A pad cut into a slope might be 900mm deep on the high side and nothing at all on the low side.

The usual way around this is to take an average. Mark out the area, measure the depth of cut at regular points across it, add the measurements together and divide by how many you took. More points give you a better answer. On a simple, even slope, the average of the deepest and shallowest points gets you in the right range.

So a pad 12 metres by 8 metres that runs from 900mm deep down to nothing on an even slope averages about 450mm, or 0.45 metres. That works out to 12 × 8 × 0.45, which is about 43 cubic metres in the ground.

If you are levelling a backyard rather than cutting a house pad, the same thinking applies, and we cover the bigger picture in our guide to what it costs to level a sloping backyard.

Why the Pile Is Bigger Than the Hole

Here is the part that surprises people. Dig 30 cubic metres out of the ground and you do not end up with a 30 cubic metre pile. You end up with something noticeably bigger.

Soil in the ground is packed down. Once a bucket breaks it up, air gets in between the lumps and the whole lot takes up more room. That increase is called swell, or bulking, and every material does it to a different degree.

As a general pattern:

  • sandy soils tend to swell the least
  • clays swell more, and the stiffer the clay, the more it bulks once it is broken out
  • rock swells the most, because broken rock never packs back together the way it sat in the ground

The exact figure depends on the material, how wet it is and how it was dug, which is why we do not publish a single number for it. What matters for you is that the trucks carry the loose volume, not the hole volume, so any estimate that skips this step will come up short.

How Much a Truck Actually Carries

The obvious next step is to divide the loose volume by the size of the truck body. In practice, the truck often runs out of legal weight before it runs out of room.

Heavy vehicles have legal mass limits, and soil is heavy. Wet clay is heavier again, because water adds weight without adding any useful volume. Rock is heavier still. So a truck carting dry, sandy fill might leave with a full body, while the same truck carting wet clay can leave with a body that looks part empty, because it has reached its weight limit.

That is why the honest answer to how many truckloads is not a single sum. The truck type, the material and the weather on the day all change it. Ask any contractor what their trucks are carrying on your job and whether they are working to weight or volume. Our post on whether a site is too wet to dig explains why wet clay is a problem well beyond the truck count.

What Else Ends Up in the Trucks

The volume you calculate from the plan is rarely everything that leaves site. A few things add to it:

  • Topsoil and organic material. The top layer usually has to come off separately, and it often cannot go to the same place as the clean material underneath.
  • Batters and working room. If the sides of the cut have to be sloped back, or the crew needs room to work around footings or a wall, more soil comes out than the finished pad suggests.
  • Old concrete and buried rubbish. Old slabs, paths, footings and whatever someone buried decades ago all have to go somewhere, and they are usually handled separately from soil.
  • Rock. Basalt turns up across Melbourne's north and west, and once it is broken out it bulks up more than soil does. Our page on breaking out and carting rock covers how that side of a job works.

Where the Material Can Go

Volume is only half of the cost. The other half is where the material is allowed to go, because that decides how far the trucks travel and what each load costs at the other end.

Soil leaving a site generally needs to be classified, which means working out what it is, so it can go somewhere that will lawfully accept it. Clean natural soil has more options than material mixed with rubble, fill of unknown origin or anything that looks contaminated. If your block has a history, such as an old shed, a filled-in pool or a previous building, mention it early, because it changes where the spoil can go.

The cheapest truckload is the one that never leaves. If part of your block needs building up, balancing cut and fill on site can cut the number of loads a long way. We explain how that works in our guide to what a site cut involves, from the quote to the finished pad.

Using the Numbers When You Compare Quotes

You do not need to be exact. The point of running the numbers yourself is to know roughly what scale of job you have, so you can tell whether a quote makes sense.

When you line quotes up, check:

  • what volume each one has assumed, and whether it is the volume in the ground or the loose volume
  • whether cartage and tipping are included, or listed as extra
  • what happens to the price if the material turns out to be different from what was expected
  • how rock, concrete and rubbish are handled if they turn up

If one quote is noticeably cheaper on cartage, it is worth asking what volume it assumed and whether anything has been left out.

Getting a Proper Number for Your Dig

The quickest way to get a real truck count is to have an experienced contractor walk the site. We will measure it, look at the ground, work out where the material can go and give you a quote. You can see the earthmoving and excavation work we take on before you call. Kosta & Sons is a family run business in Tullamarine, and quotes are free after a site visit.

General information only, reflecting conditions as at October 2026. Every job is quoted after a site visit.

Ready to act on this? Explore our excavation and earthmoving services, or learn more about plant and machinery hire.

Keep reading

The quality you deserve, and dependability you can count on.

Kosta and Sons excavator working a Melbourne site at dusk

Got a block that needs work before anything can start?

Contact us right away! Let us help with your next project, from earth moving to concrete removal. We have the skills, team, and tools to make it happen.